The dry wall on the 2nd and 3rd floor of the north building is essentially complete. The heat goes on this week. The mason work should be completed over the next 2 weeks weather permitting. The roof has been completed. We have placed not only a roof drainage system, but a back up drainage system as well. The water drains via large pipes in the center of the building to prevent pipes from freezing.

The senior graphic arts students at Polytech high are participating in a design the logo competition for Eden Hill Medical Center. We hope to be able to select the logo from the winning submission. Tom Barnett