Friday, August 24, 2007





Approx 1/2 the steel is up!

Monday, August 13, 2007

Please note the following about Eden Hill. Bayhealth will be leasing space for a 9,000 sq foot imaging center (1st floor north), a 2,500 sq foot wound care center (1st floor north) and a 2,500 sq foot physical therapy unit (2nd floor north). Dr. Puri's primary care practice will be located on the second floor south--He will have the only primary care practice in the building.
The Delaware Surgery Center will be approximately 20,000 sq feet and occupy most of the 1st floor south wing. Walgreens pharmacy will be the other 1st floor south tenant directly off the main entrance. Other 1st floor tenants include Halpern Ophthamology, Halpern Optical, Lab Corp, and Express Care--the newest form of emergency care!
The 2nd floor south wing will have Surgical Associates, Reproductive Associates, Primary Care of Delaware-Dr. Puri, and Plastic Surgery practice of Dr. David Schmidt. The second floor north wing will have Urology Associates, Bayhealth PT and Tooze, Easter, Manifold Ortho, and Infusion Solutions.
The third floor will have Dedicated to Women, Glenn and Dominick, PA, Delaware Heart and Vascular, Kent Foot and Ankle, Dr. Medlin-Dentistry, Center for Cosmetic and Reconstructive Surgery-Dr. Carey and Delaware Back Pain-Dr. Rachel Smith et al.--Tom B

Friday, August 10, 2007

STEEL IS GOING UP






A large portion of the site work has been completed. The three stories of steel are going up quickly. Next Friday a second crane will be erected on site to make double time with the steel erection. I am happy to report that we have interest in a second building. This building will be 30,000 sq feet and be located along Banning Street. From the aerial view it is just before the dirt piles in the upper right. My daughters, Olivia and Elizabeth, are shown having fun at the site. Pictured above is Ed Thwaites, project superintendent for Asset Builders. He and Bob Wood of Asset made a site suggestion that saved Eden Hill Medical Center over $200,000! --Tom Barnett

Tuesday, August 7, 2007



The crane has been erected and the first pieces of steel are going up! The footers for the front door have been poured.

Friday, August 3, 2007




Work continues at the site---The final footers at the front door were poured today. The footer work was completed twice as fast as usual per the "Walker" company foreman. The steel will be delivered on Monday and Tuesday and start to be erected on Tuesday, Aug 7, 2007. The pond work is 98% complete. The pipes coming into the pond have been set. The grading of the site continues. About 6,000 yards of fill dirt still need to be transferred from the east side of the property to the west side. In addition we have 30,000 yards of topsoil that needs to be taken off site. Essentially if someone is willing to transport it off site it is theirs! Otherwise we will have to pay $102 per truck load (2-3,000 truck loads) to transport it off site. --Tom Barnett